Solution : https://service.sap.com/sap/support/notes/1424698 (SAP Service marketplace login required)
Summary :
Despite active availability control, there are instances where the assigned value for an order or WBS (Work Breakdown Structure) element exceeds the planned budget or releases. This discrepancy is primarily observed in the "Assigned" values displayed in SAP transactions KO22/KO23 for orders, and CJ30/CJ31 or CJ32/CJ33 for WBS elements. The issue stems from potential program errors where the assigned value updates fail, resulting in no immediate error detection until a subsequent recalculation (e.g., using transaction KO31). Typically, this leads to assignments beyond the set budget thresholds defined within the system’s tolerance limits, thus bypassing automatic error alerts intended to prevent such overspending.
Key words :
1000 usd nnnn 700 usd 0 usd nnnn+1 300 usd 0 usd, 1000 usd nnnn 700 usd 700 usd nnnn+1 300 usd 0 usd, 1000 usd nnnn 700 usd 0 usd nnnn+1 300 usd 700 usd, 1000 usd nnnn 0 usd 700 usd nnnn+1 1000 usd 0 usd, 1000 usd nnnn 700 usd 800 usd, 1000 usd 0 usd nnnn 700 usd, 1000 usd 800 usd nnnn 700 usd, revaluation availability control error messages, transaction group activity usage ++, subsequent fiscal year nnnn+1
Related Notes :
1414563 | Different assigned values in availability ctrl and reporting |
1245966 | Activating the availability control for activation type 1 |
1160675 | Availability check, commitment carr. fwd. and budget crryfd |
991431 | Availability control for scheduling maintenance plans |
865855 | Warnings and not errors issued for assess., distr.,and so on |
783161 | Availability control check only if assigned value increases |
696362 | Exit: Availability control for valuated goods receipts |
430451 | Activating avail. ctrl for budget distributn to WBS element |
320470 | CJCO, KOCO: Which costs are used for the budget carryforward |
178837 | Availability control: Incorrect assigned value? |
46209 | No availability control for goods receipts |