SAP Table VSPRTE_CN - Version: Scheduling data for project item

Field Key Data Element Type Offset Leng Decimals Check Table Text
MANDT X MANDT CLNT 0 3 0 T000 Client
VSNMR X VSNMR CHAR 3 12 0 Number or description of a version
POSNR X PS_POSNR NUMC 15 8 0 PRPS WBS Element
PSPHI PS_PSPHI NUMC 23 8 0 PROJ Current number of the appropriate project
PSTRT PS_PSTRT DATS 31 8 0 WBS element: Basic start date
ESTRT PS_ESTRT DATS 39 8 0 Forecasted start date of the WBS element
ISTRT PS_ISTRT DATS 47 8 0 Actual start date for the WBS element
PENDE PS_PENDE DATS 55 8 0 WBS element: Basic finish date
EENDE PS_EENDE DATS 63 8 0 Forecasted finish date of the WBS element
IENDE PS_IENDE DATS 71 8 0 Actual finish date of the WBS element
PDAUR PS_PDAUR QUAN 79 5 1 Length (duration) of the basic dates in the WBS element
EDAUR PS_EDAUR QUAN 82 5 1 Forecasted length (duration) of the WBS element
IDAUR PS_IDAUR QUAN 85 5 1 Actual length (duration) of the WBS element
IEINH PS_IEINH UNIT 88 3 0 Unit for duration of actual WBS element dates
EEINH PS_EEINH UNIT 91 3 0 Unit for duration of WBS element planned dates
PEINH PS_PEINH UNIT 94 3 0 Unit for duration of basic WBS element dates
FLGVG PS_FLGVG CHAR 97 1 0 Indicator: There are activities for the WBS elements
FLGEW PS_FLGEW CHAR 98 1 0 Indicator: Expected dates from the activities
FLGEM PS_FLGEM CHAR 99 1 0 Indicator: Forecast dates set manually
FLGVM PS_FLGVM CHAR 100 1 0 Indicator: Basic dates set manually
FLGIM PS_FLGIM CHAR 101 1 0 Indicator: Actual dates set manually
FLGVI PS_FLGVI CHAR 102 1 0 Indicator: Actual dates from the activities
PSTRM PS_GSTRS DATS 103 8 0 Earliest scheduled start date (Basic)
PETRM PS_GLTRS DATS 111 8 0 Latest scheduled finish date (basic)
ESTRM PS_GSTPP DATS 119 8 0 Scheduled start date (Forecast)
EETRM PS_GLTPP DATS 127 8 0 Latest scheduled finish date (Forecast)
VISTR PS_ISTVORL DATS 135 8 0 Tentative actual start date for WBS element
VIEND PS_IENVORL DATS 143 8 0 Tentative actual finish date for WBS element
PSTRS PS_GSTRE DATS 151 8 0 Latest scheduled start date (basic)
PETRF PS_GETRE DATS 159 8 0 Earliest scheduled finish date (basic)
ESTRS PS_GSTRP DATS 167 8 0 Latest scheduled start date (forecast)
EETRF PS_GLTRP DATS 175 8 0 Earliest scheduled finish date (forecast)