SAP Note 785903 - Requirements and availability dates for planned orders

Component : Requirements Planning/Planned Order -

Solution : https://service.sap.com/sap/support/notes/785903 (SAP Service marketplace login required)

Key words :
order start date' date adjustment, detiled scheduling takes place, order start date', order start date, basic date check, standard sap system, requirements date/time, lead time scheduling, factory calendar check, 'adjust basic dates

Related Notes :

893416Latest requmnt date/time must be between requmnt date/time#
611153APO<->R/3: Planned order dates check (modification)
600194APO<->R/3: Planned order dates check in SAP R/3
582320MD11/MD12:Error during basic date determin. in planned order
578553APO->R/3: Planned orders on non-workdays
501224Additional information about the 'X0' MRP type
161028MOD: Planned order scheduling via APO interface