SAP Note 611153 - APO<->R/3: Planned order dates check (modification)

Component : Requirements Planning/Planned Order - Material Requirements Planning

Solution : https://service.sap.com/sap/support/notes/611153 (SAP Service marketplace login required)

Summary :
After installing OSS notes 578553 and 582320, issues are observed in SAP R/3 concerning the non-verification against the factory calendar for planned order basic dates and requirement dates of components when the header material is integrated into SAP APO. The problem arises because materials remain planned in SAP R/3 even though SAP APO acts merely as an ATP server. The solution involves implementing a modification that ensures the factory calendar check is always executed in SAP R/3. Additionally, Note 700535 must also be applied. This fix will revert the system behavior to pre-installation status of the specified notes.

Key words :
planned order basic dates, instalation os oss notes 578553, terms planned order, active integration model, factory calendar check, prerequisites header material, basic date, oss-notes 578553, factory calendar, header material

Related Notes :

893416Latest requmnt date/time must be between requmnt date/time#
785903Requirements and availability dates for planned orders
710366R/3-APO: Planned order opening date too late in R/3
700535Error message when creating a planned order
617859APO<->R/3: Planned order dates check in SAP R/3 (follow-up)
600194APO<->R/3: Planned order dates check in SAP R/3
582320MD11/MD12:Error during basic date determin. in planned order
578553APO->R/3: Planned orders on non-workdays