Solution : https://service.sap.com/sap/support/notes/622299 (SAP Service marketplace login required)
Summary :
This SAP Note elucidates the functionality of the availability check in material planning. It defines the process flow when creating or modifying sales orders that invoke this check, considering various planning strategies and the assignment of requirement types and classes. For constraints like the unavailability of the ATP setting in customer requirements, appropriate transactions such as OVZH, OVZG, and OMPO are suggested for checking and modification. The provided examples illustrate scenarios like planning without final assembly, with distinctions among consumption and allocation indicators guiding the availability verification processes across different planning setups.
Key words :
independent requirements quantities exist period planned independent requirements week 1 50 pc week 2 50 pc week 3 50 pc week 4 50 pc week 5 50 pc week 6 50 pc, reqmt customer requirement week 1 50 pc week 2 50 pc week 3 50 pc week 4 50 pc week 5 0 pc 250 pc week 6 0 pc, note answers frequently asked questions, replenishment lead time receive confirmation dates, maximum backward consumption period, -consumed planned independent requirements, consumed planned independent requirements, free planned independent requirements, planned independent requirements quantities, newly created customer requirements
Related Notes :
835219 | FAQ: ATP composite note |
460569 | Planning check in VA02: Shift of confirmation |
312152 | Planning check: Sales order <--> rescheduling |
171556 | Consumption of planned independent requirements |
106104 | Adjustment period during availability check |
78837 | No planned independent rqmts availability because of DZEIT |
43102 | MD82, VA02:Confirmed quantities no longer available |