SAP Note 171556 - Consumption of planned independent requirements

Component : Demand Management -

Solution : https://service.sap.com/sap/support/notes/171556 (SAP Service marketplace login required)

Summary :
This SAP Note addresses issues in date discrepancies within the availability check against planning, particularly in Transactions MD73 and MD04. The problem stems from the logic used in program planning and materials planning that handles the consumption of planned independent requirements. SAP’s detailed solution outlines how all existing and planned requirements are determined and consumed in these transactions. The note clarifies the program logic, emphasizing the importance of proper settings for consumption mode and periods. It describes various scenarios and outcomes, ensuring a robust guide on managing and debugging related discrepancies.

Key words :
consumedperiod_1 100 requirement_1 50                                        requirement_2 30                                        requirement_3 20period_2 200 requirement_4 100                                        requirement_5 40                                        requirement_6 60period_3 300 requirement_8 130                                        requirement_9 50                                        requirement_7 120period_4 100 requirement_7 50                                        rel 50however, consumedperiod_1 100 requirement_1 50                                        requirement_2 30                                        requirement_3 20period_2 200 requirement_4 100                                        requirement_5 40                                        requirement_6 60period_3 300 requirement_7 170                                        requirement_8 130period_4 100 requirement_9 50                                        rel 50example 1, consumedperiod_1 100 requirement_1 50                                        requirement_2 30                                        requirement_3 20period_2 200 requirement_10 60                                        requirement_4 100                                        requirement_5 40period_3 300 requirement_6 60                                        requirement_7 170                                        requirement_8 70period_4 100 requirement_8 60                                        requirement_9 40, date planned independent requirements requirements, save unconfirmed customer requirements, planned independent requirements sorted, remaining planned independent requirements, overview lists md73/md04, requirement_4, system-internal consumption situation

Related Notes :

622299Consulting: Availability check against planning
456188Confirmatn for automatic availability check against planning
312152Planning check: Sales order <--> rescheduling
189748Error in planning check
165039
64270
43102MD82, VA02:Confirmed quantities no longer available