SAP Note 525433 - PPM generation with lot size margin: consumption det.

Component : Production Process Model -

Solution : https://service.sap.com/sap/support/notes/525433 (SAP Service marketplace login required)

Key words :
multi mix resource fixed bucket consumption = variable duration + fixed duration, multi mix resource fixed bucket consumption = fixed duration, single mix resource fixed bucket consumption = fixed duration, multi mix resource fixed bucket consumption = duration, single mix resource fixed bucket consumption = duration, - matrix        variable bucket consumption = variable duration + fixed duration, calculated        variable bucket consumption = variable duration + fixed duration, multi mix resource fixed bucket consumption, single mix resource fixed bucket consumption, resource variable bucket consumption = variable duration

Related Notes :

781962PPM generation: SNP was generated without bucket consumption
441102Consulting notes in PP/DS