SAP Note 423626 - Different dates in R/3 and APO

Component : PP-DS / Production and Process Order - Interfaces

Solution : https://service.sap.com/sap/support/notes/423626 (SAP Service marketplace login required)

Summary :
This SAP Note addresses discrepancies in order dates between R/3 and APO systems. The issue arises when orders configured in R/3 and sent to APO display differing start and end dates due to APO's scheduling based on the integration strategy profile. To synchronize date data, manual adjustment in APO or an active automatic back-update from APO to R/3 must be employed; functionalities like such are available from APO 3.0 onwards. The statuses EXTS and DSEX respectively at header and operation level confirm order transmission from APO to R/3. Solutions include referencing linked notes and configuring settings in transaction /SAPAPO/CP3 in APO for automatic update entries.

Key words :
transaction /sapapo/c5 aftr completing, call transaction /sapapo/cp3, -house production publication type, activate automatic back update, automatic back-update, integrated operations confirm, terms production order, production order, production orders, planned order

Related Notes :

1167219Handling order conversion in dynamic setup scenario
774934Deltareport for planned orders w/out APO operat.: Error 161
770838Deltareport3 shows date differences for planned orders
761114R/3: MRP-run reschedules APO planned orders
722320R/3 -> APO: Order could not be scheduled
684356Date transfer between R/3 and APO
446866Documentation on runtime information for publishing
417461Scheduling error transferring orders to APO
394113Date shift between R/3 and APO