Solution : https://service.sap.com/sap/support/notes/24222 (SAP Service marketplace login required)
Summary :
In an SAP environment, positive lead-time specified in the MRP data of BOM components does not impact the scheduling of planned orders due to the lead-time scheduling processes. Instead, when routing is applied for scheduling, material components' requirements dates are derived directly from operation dates, making the positive lead-time entries superfluous for scheduling purposes. It is essential that during initial planning and BOM entry, the positive lead-time reflects the necessary interval from the order start to the related operation start, particularly if scheduling omits routing-based calculations.
Key words :
terms negative lead time, entered positive lead time, positive lead-time, positive lead time, bom component makes, higher-level assembly, lead time scheduling, time interval, planned orders, requirements planning
Related Notes :
386279 | Lead time/lead-time offset in planned order |
366348 | Lead-time offsets ignored after dispatching |
152319 | Consulting: Scheduling of planned order for routing |