Description This report lets you carry out internal activity allocation of businessevents between the organizer and the instructor by means of credit anddebit memos. During this process, the cost center of the account assignment object(receiving cost center) specified is debited and the instructor's(sender) cost center is credited. Instructor fees can be distributed on a percentage basis to accountassignment objects (cost center, order, PSP element and project). Fund Accounting objects (fund, function area, grant) can also betransferred to CO when Fund Accounting is active. In addition, you can cancel documents for instructor costs alreadyallocated and, if instructor costs have not yet been allocated, you canchange activity price data or cost center assignment data. Note> You can specify the cost distribution and account assignment data whenthe report is executed. These specifications are saved when you performactivity allocation.Integration You activate integration with Cost Accounting (CO) for activityallocation purposes in Customizing for Training and Event Managementunder Internal Activity Allocation>.Preconditions
- The cost items must be maintained for the resource type 'instructor'
- The instructor's cost center assignment must be maintained.
- The account assignment object (cost center/order/PSP element) must be
maintained.
- The sender cost center must be maintained.
- The sender cost center and the account assignment object must be in the
same controlling area.
- The activity type must be maintained.
Note> To be able to use the internal activity allocation functions, you mustfirst create a network of activities. You must define plannedactivities and prices and the relevant activity types for the costcenters involved in the allocation process. For Training and EventManagement purposes, however, it is sufficient to plan the activityprice of the sender cost center together with the activity type set inCustomizing in the step DS:SIMG.SIMG_OHP3OOCA>Specify Activity Types >. The following points regarding activity type>are important: ACTIVITY CATEGORY> = 1 (manual entry andallocation) with the corresponding cost element (see point 2) COST ELEMENT>= secondary (internal allocationscreated by you, the customer) cost element type = 43 (internal activity allocation) Planning activities/activity prices activity price = 1Features Selection You can set parameters to determine the data output by the report: Business event selection> There are a number of ways to start the report: Enter one or more business event groups>. The system finds all ofthe business events belonging to the specified group(s) and lists theinstructors. Enter one or more business event types>. The system finds all ofthe business events and instructors belonging to the specified type(s). Enter one or more business events> whose instructor costs are tobe allocated. You specify the instructor(s)> by selecting the object type andentering the name(s). The system offers you all object types to whichindividual persons can be assigned for selection. Reporting period> Enter the exact period for which you want to determine instructors forallocation. List output> You can specify whether the report should output instructors that arenot yet allocated>, already allocated > or can beallocated> for the events specified. Document date> Enter a date in this field if you want to change the default date ofthe activity allocation. This date is used purely for informationpurposes. The default date is usually the current date. Posting date> The date in this field indicates when costs are to be posted to CO, inother words, the settlement period. The default date is usually thebusiness event start date>. You can overwrite this date asrequired. Example> You want to perform activity allocation for the instructor of an eventthat started on February 2 of this year. However, you want costsallocated in the second quarter rather than in the first quarter. Inthis case, you enter April 2 of this year as the posting date>. Standard selection screen> If you select this indicator and choose Execute>, you access themore detailed selection screen of the main report RHINLV10 before thereport is run. Note> On the selection screen of the main report you can search for objectsby 'status', for example. As a rule, it is not necessary to go to themain report since the selection screen of the pre-report offerssufficient selection options. If you do not want to access the detailedselection screen, do not activate this option before choosingExecute>.Output The report outputs a list containing the following information perbusiness event:
- Business event:
- Instructor
- Resource type
- Sender cost center
- Activity type
- Activity allocation price
- Account assignment object(s) (e.g. receiving cost center)
- Document number
On the list screen, you can distribute instructor costs temporarily ona percentage basis to different account assignment objects:
- Cost centers
- Internal orders
- PSP elements (projects)
You can perform activity allocation> from the list screen. If you select the instructors for activity allocation and chooseCreate activity allocation>, all activity allocation data istransferred to CO. The following process flow takes place: A validation check is performed on the document items. If the items are validated, a reference document is generated with thestatus transfer designated>. The BAPI/ALE for the activity allocation is called. The status of the reference document changes to transfer effected> (yellow/amber light). Due to the fact that the systems may be decoupled (CO and PE indistributed systems), confirmation of this transaction is necessary toensure that the transaction has actually been executed. For this purpose, you must call the function Compare document>.The system searches for the original CO document. If it finds the original document, the status of the reference documentchanges to Transfer confirmed> (green light). You can display the original document by choosing View> ->Ref. <-> Original document>. If the original document cannot be found, the status of the referencedocument changes to Transfer incorrect> (red light). For more information on the procedure when the original document cannotbe found, refer to Error diagnosis>. You can execute the following functions from the list screen>:
- Display the document flow> for business event, in other words,
all of the relevant allocation data that exists for the business event.(The cursor must be positioned on the business event.)
- Display the document flow> for the instructor, in other words,
all of the relevant allocation data that exists for the instructor.(The cursor must be positioned on the instructor.)
- Display document> (reference document)
- Display error log> (confirmations of check/execution of activity
allocation)
- Check> whether the relevant data can be allocated. This function
also checks whether the settlement period is closed, in which case,data transfer to CO is not allowed.
|