This SAP Note addresses issues with unnecessary rescheduling of manufacturing orders in APO following changes in R/3 (such as order release or adding operations). Implement structural enhancements mentioned in note 553876 to resolve this. The solution involves implementing corrections from this note, part of a larger cross-integration effort detailed in the implementation guide in note 572644 and consulting note 579758, which outlines further prerequisites and restrictions.
Key words :
initial data transfers, compare/reconcile function, terms manufacturing order, cross-integration correction, manufacturing order, production order, process order, planned order, customer exit, date transfer
Related Notes :
634468 | APO->R/3: New explosion deletes resource and capacity reqmt |
612542 | Retaining dates for phases of partially confirmed operation |
608057 | Date retention for phases of partially confirmed activity |
607231 | R/3->APO: ATP triggers rescheduling in SAP APO |
597713 | Activity date retention: RC59 f. planned order modification |
590514 | Prop. quant. adjustm.: Install. probs. through note 587917 |
588219 | Retaining activity dates: Adjusting header material dates |
587917 | Deactivating the activity date transfer per order |
586685 | Activating retention of activity dates |
586663 | Deactivation by order of activity date retention |
583754 | BADI: Prop. quantity adjustment & retaining activity dates |
581698 | R/3->APO: Retention of activity dates in APO |
581553 | R/3->APO: Retention of activity dates in APO |
579883 | R/3->APO: Specifying the initiator of an R/3 transfer |
579758 | R/3->APO: Retaining APO scheduled activity dates |
578079 | APO->R/3: Re-explosion deletes resource & capacity reqt. |
572644 | Retaining activity dates: Implementation |
554771 | R/3->APO:Loss of component features from PPM |
551409 | Addition of field CIFTRIGGER to the structure CIFCTRLPAR |
549496 | APO 3.1: operations differ in R/3 and APO |
508365 | Order not created in the planning segment |
507247 | Duplicate co-products after BOM has been changed |