Solution : https://service.sap.com/sap/support/notes/409150 (SAP Service marketplace login required)
Key words :
reference type complete_exp type char1, create normal function module chgr_check_order_complete, individual network activities exist, lower-level wbs elements, lower-level wbs element, project cost plan reason, reference type i_prps_tab, displayed wbs elements, higher-level path, wbs element assignment
Related Notes :
521116 | CJ27/CJV1: Calculate costs / Call cost report |
510854 | CJ2B:Short dump during costs/revenue determination |
501384 | CJ2B: Calculate costs if dates are not current |
494677 | CJ2B: short dump during costs/revenue calculation |
484925 | CJ2B: Determine costs / determine revenues incorrect |
434525 | CJ2B: Error within cost/revenue calculation |
412725 | CJ2B: Costs not updated after costing |
374396 | Call of planning board: Displayed objects |