SAP Note 194019 - Basic dates, production start are incorrect

Component : Scheduling -

Solution : https://service.sap.com/sap/support/notes/194019 (SAP Service marketplace login required)

Summary :
This SAP Note addresses mismatches in order start dates and first operation dates occurring when the "Adjust basic, dates" setting is improperly scheduling orders based on the workday schedules of standard, rather than specific, factory calendars. Additionally, flawed determination of order finish dates arises if the in-house production time is set to zero. To rectify, implement specific correction instructions and patches outlined in the Note and several required prerequisite Notes (e.g., 135949, 78802, 83488). Post-implementation, further updates provided by additional Notes (e.g., 205059, 206533, 209109) should be applied to ensure comprehensive resolution.

Key words :
incorrect scheduled start date occurs, additional key words co02, scheduled start date, order finish date, -house production time, adjust basic dates, start date, scheduled dates, basic dates, production dates

Related Notes :

516490Latest finish 00:00:00 instead of 24:00:00 hrs
388537Basic date has incorrect time (00:00 / 24:00)
387440Incorrect start date when order duration is 0
338715Order with zero duration: basic dates incorrect
330384Basic finish at incorrect time: 00:00 / 24:00
322898Basic date change for 'Only capacity requirements'
318616Plnd ordr:Ordr start date later thn ordr finish dte
316022IW70: Scheduling with the incorrect capacity version
310919Incorrect dates at date limit
310714MF50: basic finish date changes with night shift
215792Basic dats incor. (night shift + float after prod.)
212126End of prod.incor. (24:00 instead of 00:00 o'clock)
210365Requirements dates of material components empty
209109Basic dates are on non-working day after adjustment
206533Order finsh dte in planned order adjustd incorrctly
205059Adjust basic dates with scheduling margin key
182364Adjust basic dates incor. w/ scheduling margin key
159907Order finish date: Scheduling with production dates
157890Basic date empty after scheduling
135949Production start date is on non-working day
128170Order finish date is incorrect for scheduling type '3'
117124Order: order start date is one day too early
107004Repet.manufactrng:ordr finish date one day too late
97817Order start date one day too early or too late
96107Order: scheduling with 'Adjust basic dates'
90645"Today"sched.:ord.finish date before ord.start date
83488Basic dates fall on a non-working day
78802Pld.order:Order finish date before order start date