Solution : https://service.sap.com/sap/support/notes/194019 (SAP Service marketplace login required)
Summary :
This SAP Note addresses mismatches in order start dates and first operation dates occurring when the "Adjust basic, dates" setting is improperly scheduling orders based on the workday schedules of standard, rather than specific, factory calendars. Additionally, flawed determination of order finish dates arises if the in-house production time is set to zero. To rectify, implement specific correction instructions and patches outlined in the Note and several required prerequisite Notes (e.g., 135949, 78802, 83488). Post-implementation, further updates provided by additional Notes (e.g., 205059, 206533, 209109) should be applied to ensure comprehensive resolution.
Key words :
incorrect scheduled start date occurs, additional key words co02, scheduled start date, order finish date, -house production time, adjust basic dates, start date, scheduled dates, basic dates, production dates
Related Notes :
516490 | Latest finish 00:00:00 instead of 24:00:00 hrs |
388537 | Basic date has incorrect time (00:00 / 24:00) |
387440 | Incorrect start date when order duration is 0 |
338715 | Order with zero duration: basic dates incorrect |
330384 | Basic finish at incorrect time: 00:00 / 24:00 |
322898 | Basic date change for 'Only capacity requirements' |
318616 | Plnd ordr:Ordr start date later thn ordr finish dte |
316022 | IW70: Scheduling with the incorrect capacity version |
310919 | Incorrect dates at date limit |
310714 | MF50: basic finish date changes with night shift |
215792 | Basic dats incor. (night shift + float after prod.) |
212126 | End of prod.incor. (24:00 instead of 00:00 o'clock) |
210365 | Requirements dates of material components empty |
209109 | Basic dates are on non-working day after adjustment |
206533 | Order finsh dte in planned order adjustd incorrctly |
205059 | Adjust basic dates with scheduling margin key |
182364 | Adjust basic dates incor. w/ scheduling margin key |
159907 | Order finish date: Scheduling with production dates |
157890 | Basic date empty after scheduling |
135949 | Production start date is on non-working day |
128170 | Order finish date is incorrect for scheduling type '3' |
117124 | Order: order start date is one day too early |
107004 | Repet.manufactrng:ordr finish date one day too late |
97817 | Order start date one day too early or too late |
96107 | Order: scheduling with 'Adjust basic dates' |
90645 | "Today"sched.:ord.finish date before ord.start date |
83488 | Basic dates fall on a non-working day |
78802 | Pld.order:Order finish date before order start date |