SAP Note 1296927 - PI dummy activities not allowed to have input/output nodes

Component : PP-DS / Production and Process Order - Requirements Planning/Planned Order

Solution : https://service.sap.com/sap/support/notes/1296927 (SAP Service marketplace login required)

Summary :
When converting a planned order to a process order in SAP, the process fails to reflect in the SCM system due to incorrect assignment of components within the master recipe. Specifically, components assigned to an operation rather than a phase cause SAP liveCache termination with error message "/SAPAPO/OM_ERROR 315". To rectify this, components should be reassigned to phases, the affected queue cleared, and the process order retransferred to SCM using R/3 report RCIFOORDT or a delta report.

Key words :
message number /sapapo/om_error 315, /sapapo/om 102 reason, pi dummy activities, input/output nodes, scm apo system, /sapapo/om_error315, scm system, dummy operation, input materials, planned order

Related Notes :

1315466Error in Process order Creation or Transfer from R/3
1300646Wrong output assignment in key completion queue
627630Report for transferring production/planned orders