SAP Note 501384 - CJ2B: Calculate costs if dates are not current

Composant : Project Planning Board -

Solution : https://service.sap.com/sap/support/notes/501384 (Connexion à SAP Service Marketplace requise)

Mots Clés :
system generates dialog 'determine costs', execute function 'calculate costs', project planned costs, project planning board, status i0118 'ntup', attached program corrections, status 'ntup', program error, terms ntup, wbs elements

Notes associées :

521116CJ27/CJV1: Calculate costs / Call cost report
510854CJ2B:Short dump during costs/revenue determination
494677CJ2B: short dump during costs/revenue calculation
484925CJ2B: Determine costs / determine revenues incorrect
434525CJ2B: Error within cost/revenue calculation
412725CJ2B: Costs not updated after costing
409150Problems with the costs display in project planning board
381591CJ2B: Calculate costs for activities
212422Costs for network are not stored
199040Updating cost information on planning board