SAP Note 135949 - Production start date is on non-working day

Composant : Scheduling -

Solution : https://service.sap.com/sap/support/notes/135949 (Connexion à SAP Service Marketplace requise)

Mots Clés :
additional key words co01, copy source code corrections, production start date, -house production time, production dates, -working day, scheduled backwards, material master, operation segments, duration greater

Notes associées :

194019Basic dates, production start are incorrect
130401Sub-operation/work element has incorrect dates
108427Operation dates before production start date