SAP Note 121506 - Order finish date is before production finish date

Composant : Scheduling -

Solution : https://service.sap.com/sap/support/notes/121506 (Connexion à SAP Service Marketplace requise)

Mots Clés :
additional key words co02, order finish date, production finish date, order float, production orders, process orders, night shift, workday preceding, work center, program error

Notes associées :

310714MF50: basic finish date changes with night shift
97817Order start date one day too early or too late
83488Basic dates fall on a non-working day