SAP Note 102687 - Forecast set of dates: activity on non-working day

Composant : Scheduling -

Solution : https://service.sap.com/sap/support/notes/102687 (Connexion à SAP Service Marketplace requise)

Mots Clés :
additional key words cn21, forecast set, activity dates, -working days, work center, factory calendar, forecast duration, forecast scheduling, forecast dates, program error

Notes associées :

516490Latest finish 00:00:00 instead of 24:00:00 hrs
120149Operation dates in the process order
45759Scheduling for exact date with work center